Browse
(440) 299-7778
Menu
(440) 299-7778
One-year parts and labor warranty30-day money-back guaranteeEnglishEspañolContact

The text of a manual · part 15 of 56

Trimble Survey Controller User Guide: Roading, pages 125 to 134

Pages 125 to 134 of 504, from Trimble Survey Controller User Guide

The original document is the PDF (5.9 MB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.

For the Trimble TSCe

Page 125

Roading

6

Figure 6.2 shows how the Horizontal and Slope options are used in the Construction H.Offset applied field. The construction V.Offset value in the diagram is 0.000. Stake Construction H.Offset applied field set to Slope

Point selected for stakeout

Construction H.Offset applied field set to Horizontal

Previous template element

Construction H.Offset

Figure 6.2

Options in the Construction H.Offset applied field

3.

If there is a value in the Construction H.offset field, the Trimble Survey Controller software directs you to a point that is offset from the design point. A negative value offsets the point towards the centerline (in). A positive value offsets the point away from the centerline (out). Note – If you enter a value for the Construction H.Offset on the centerline (at offset 0.00 m), a negative value offset is to the left.

4.

If there is a value in the Construction V.Offset field, the Trimble Survey Controller software directs you to a point that is offset vertically from the design point, as follows: –

A negative value offsets the point vertically down.

–

A positive value offsets the point vertically up.

Trimble Survey Controller User Guide

101

Page 126

6

Roading

Note – Construction offsets are not automatically applied to a side-slope offset. For more information, see page 110. Construction offset values specified here are not applied to a DTM surface.

6.4.4

Navigating to a Point on the Road The navigation process that the Trimble Survey Controller software uses depends on whether you are staking out a non-side-slope point or a side-slope point. Note – Before navigating to the point in a GPS survey, make sure that the survey is initialized. For more information, see RTK Initialization Methods, page 264. Icons in the graphical display screen Table 6.3 lists the icons that appear in the top right of the graphical display screen when you stake out a point on a road. (The graphical display screen is shown in the next section.) Table 6.3 Icon

Icons in the graphical display screen Information about the point staked out The point is on the left side of the road and is in cut.1 The point is on the left side of the road and is in fill.2 The point is on the right side of the road and is in cut. The point is on the right side of the road and is in fill.

1

Cut means that the elevation of the design point is lower than the current position.

2 Fill means that the elevation of the design point is higher than the current position

10 2

Trimble Survey Controller User Guide

Page 127

Roading

6

Note – In addition, for side-slope positions the slope value is displayed below the icon. For non-side-slope positions the code (or offset value if no code is assigned) is displayed below the icon. Navigating to a non-side-slope point x

To navigate to a non-side-slope point: 1.

. The Stakeout graphical display Select a point and tap screen appears. If you are using a conventional instrument, refer to the screen on the right:

The station value for the point appears at the top of the screen. An icon to the right indicates: – the side of the road on which the point lies

– whether the point is in cut or fill

– the code (or offset value, if no code is assigned) for the point

For more information, see Table 6.3.

Trimble Survey Controller User Guide

103

Page 128

6

Roading

The left side of the screen shows the compass arrow, and the right side of the screen displays values in the following fields. Table 6-4 shows these fields and the equivalent field in a conventional survey. Table 6-4

Non-side-slope point fields

Field

What it shows

In a conventional survey, this field is replaced by ...

Azimuth

Azimuth to the point.

Go In (or Go Out).

Horizontal Distance

Horizontal distance to the Go Left (or Go Right). point. This value is also shown at the bottom of the graphical display screen.

Vertical Distance Distance between the (cut/fill) present position and the design position being staked out. Road: Go Forward (or Go Backward)

Distance from the current position to the point, relative to the road. Forward is towards the end station, backward is towards the start station.

Road: Go Left (or Distance from the current Go Right) position to the point, relative to the road. If you are facing the end station, “Left” is on your left.1 1 The forward/backward and right/left values are relative to the cross-section of the point being staked out (see Figure 6.3). They are not relative to the current direction of travel or to the current stationing and they do not represent delta stationing and offset values for points on curved sections of the road. If you are using a conventional instrument, the road values only appear after you take a distance measurement.

10 4

Trimble Survey Controller User Guide

Page 129

Roading

6

Figure 6.3 shows an example of the forwards direction and the right direction when staking out a point.

Direction of increasing stationing

Forwards

Right

Figure 6.3

2.

Forwards direction and right direction

Use the graphical display or the text display to navigate to the point. Do one of the following: –

If you are using a conventional instrument, see Using the Graphical Display During Stakeout, page 381.

–

If you are using GPS, use the arrow as a guide and start moving towards the point, holding the TSCe data collector in front of you. The arrow points in the direction of the point to be staked out. When you walk towards the point, the arrow points to the top of the screen. Note – The direction arrow only works correctly when you are moving. Always move forward towards the point.

Trimble Survey Controller User Guide

105

Page 130

6

Roading

When you get closer to the point, the arrow disappears. Instead, a bull’s-eye symbol represents the point, and a cross represents your position, as shown in the following screen:

Note – When you navigate to a non-side-slope point with construction offsets, the bull’s-eye symbol represents the offset point.

10 6

F

3.

to go into Fine mode. For more information, see Fine Tap and Coarse Modes, page 309.

4.

When you are on the point, the cross covers the bull’s-eye symbol. Check the precisions and mark the point.

Trimble Survey Controller User Guide

Page 131

Roading

6

Note – The symbol that shows the position of the point also shows the road-space coordinate frame. Figure 6.4 shows how the long line points in the direction of increasing station, while the short line points in the direction (left to right) of increasing offset.

Direction of increasing stationing Direction of increasing offset (right side of road)

Figure 6.4

5.

Point icon in the graphical display screen

Do one of the following:

9

–

Measure the point. For more information, see Measuring the As-Staked Position, page 113.

–

To stake out another point, tap out road screen.

to return to the Stake

Trimble Survey Controller User Guide

107

Page 132

6

Roading

Navigating to a side-slope point To navigate to a side-slope point: 1.

x

. The Stakeout graphical Select a side-slope point and tap display screen appears. If you are using a conventional instrument, refer to the screen on the right:

The station value for the point appears at the top of the screen. An icon to the right indicates: – the side of the road on which the point lies

– whether this is a cut slope or a fill slope

– the slope value of the side-slope

For more information, see Table 6.3, page 102. Note – For side-slope offsets where the slope changes between templates, the Trimble Survey Controller software calculates the side-slope for intermediate stations by interpolating the slope value. The screen shows a graphical display and text. The fields that appear are the same as those which appear in the display for a non-side-slope point, as shown on page 103.

10 8

Trimble Survey Controller User Guide

Page 133

Roading

6

Note – Values in the ∆Backward (or ∆Forward) and ∆Left (or ∆Right) fields are relative to the cross-section of the point that is being staked out. They are not relative to the current stationing and do not represent delta stationing and offset values for points on curved sections of the road. For more information, see Table 6.3, page 102. The graphical display also shows a dashed line that connects the side-slope catch position - the point where the side-slope intersects with the ground - to the side-slope hinge position. 2.

*

Tap to select a side-slope option. The following screen appears:

Table 6-5 explains the Select menu options for a side-slope. Table 6-5

Select menu options

Option

Description

Catch point (Auto)

The Trimble Survey Controller software selects the side-slope (cut or fill) to intersect with the ground. This is the default.

Catch point (Cut)

Fixes the side-slope as a cut side-slope.

Catch point (Fill)

Fixes the side-slope as a fill side-slope.

Trimble Survey Controller User Guide

109

Page 134

6

Roading Table 6-5

Select menu options (Continued)

Option

Description

Add Constr. offsets to Catch pt

Applies the horizontal and vertical construction offsets specified to the catch point. Navigate to the catch point before selecting this option. The position of the offset point depends on the catch point, so make sure that you stake out the catch point precisely.

Hinge point

Stakes out the base of the side-slope. This is the most direct way to select the hinge point if the template includes a ditch offset. Note: Construction offsets are not applied to the hinge point when you use this method to select the hinge point.

*

Note – Construction offsets are not automatically applied to a catch point. Navigate to the catch point and then press . Select Add Constr. offsets to Catch pt and navigate to the offset point. There is no need to tap construction offsets.

11 0

*

Trimble Survey Controller User Guide when staking out a catch point with no