Trimble Survey Controller User Guide: Roading, pages 115 to 124

Pages 115 to 124 of 504, from Trimble Survey Controller User Guide

The original document is the PDF (5.9 MB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.

For the Trimble TSCe

Page 115

CHAPTER

6 6

Roading In this chapter: ■

Introduction

■

Transferring or keying in road information

■

Reviewing the road information

■

Staking out points on the road by station and offset

■

Measuring positions on the road

Page 116

6

Roading

6.1

Introduction This chapter shows you how to stake out roads and determine your position relative to a road design. It explains how to review roading information and select a point to stake out on a road. It shows how to navigate to a non-side-slope point and a side-slope point, and measure an as-staked point.

C

6.2

Warning – Do not stake out points and then change the coordinate system or perform a calibration. If you do, these points will be inconsistent with the new coordinate system and any points computed or staked out after the change.

Transferring or Keying in Road Information Before staking out a road or determining your position relative to a road, key in or transfer a road definition. For information on how to do this, see Roads, page 134, and Templates, page 144. To transfer a road definition, use Trimble’s RoadLink™ software, which is a module of the Trimble Geomatics Office software. For more information about how to transfer files see, Chapter 4, Data Transfer. Each road is transferred as a job. To open a job, select Files / Job management. Note – Once the files are transferred, you can copy several roads into a single job. For more information, see Copying between Jobs, page 46. Each road transferred using the RoadLink software contains the coordinate system for the road. Roads always have grid coordinates.

92

Trimble Survey Controller User Guide

Page 117

Roading

6

Note – The Trimble Survey Controller software treats all road distances, including stationing and offset values, as grid distances. The value in the Distances field (accessed by selecting Configuration / Job / Cogo settings) has no effect on the road definition or the way road distances are displayed. If a ground coordinate system is defined in either the Trimble Geomatics or Survey Controller software, then the grid coordinates are, in effect, also ground coordinates.

6.3

Reviewing the Road Information To review road information in the Trimble Survey Controller software: 1.

Open the job.

2.

From the main menu, select Files / Review current job.

The following section describes the roading records that appear.

6.3.1

Roading Records Information about a road appears in the following order: 1.

The name of the road. This record includes:

•

Horizontal alignment elements – These records appear in order of increasing stationing. There is a record for each alignment element.

•

Vertical alignment elements – These records appear in order of increasing stationing. There is a record for each alignment element.

•

Template records – Templates define the cross-sections used along the road. Template records show what templates are used at the various stations along the road. There is a record each time the template changes. These records appear in order of increasing stationing.

Trimble Survey Controller User Guide

93

Page 118

6

Roading

•

Superelevation and/or widening records – There is a record each time the superelevation and/or widening changes. These records appear in order of increasing stationing.

2.

The name of the template(s). This record includes the template elements that define the cross-section of the road, starting from the centerline. Each record defines an element in the template. Note – If a road has a horizontal and vertical alignment but no templates, all offset points display a null (?) value in the V.Dist field during stakeout. If a road definition is defined only as a horizontal alignment, you can only stake it out in two dimensions. The horizontal and vertical alignments of a road do not necessarily start and end at the same stationing. When they do not, you can only stake out points in three dimensions if their stations lie within the horizontal alignment.

94

Trimble Survey Controller User Guide

Page 119

Roading

6.4

6

Staking out Points on the Road by Station and Offset Before staking out a point on the road, read General Procedure, page 308 and page 378, and Stakeout Settings, page 379.

6.4.1

Select a Point on a Road To do this:

B

1.

From the main menu, select Survey / Stakeout/Roads. A screen, similar to the following one, appears:

2.

In the Road name field, select the road to be staked out. To to view a select a road, access the Road name field and tap list of available roads, and highlight the required road.

k

V l

Tip – To review the selected road, tap now. To edit the road, tap . Use the Key in / Road screen that appears to edit the road.

3.

Tap

E to enter the name in the Road name field.

The Code field displays the code of the offset to be staked out. The Trimble Survey Controller software uses the code from the template definition for the selected offset. When the offset is 0.000 m, the code defaults to CL.

Trimble Survey Controller User Guide

95

Page 120

6

Roading

B

6.4.2

Tip – If you stake out a point and then measure it, you can edit the code in the Confirm staked deltas screen. Alternatively, store the point and then select Files / Review current job to edit the code. To change the default code for the template element, select either Key In / Templates or Files / Review current job.

4.

In the Stake field, select Station and offset.

5.

Enter a value in the Antenna/Target height field and make sure that the Measured to field is set correctly. This is especially important when staking out a catch point. The Trimble Survey Controller software can accurately locate the point only if this setting is correct.

Select the Station to be Staked Out To do this: 1.

l

Do one of the following: –

Select it from a list. To do this, highlight the Station field to display a list of stations. The following and tap screen appears:

The list contains the stations defined by the section interval, and the stations where the horizontal or vertical alignment changes.

96

Trimble Survey Controller User Guide

Page 121

Roading

6

Table 6.1 lists the abbreviations that the Trimble Survey Controller software uses. Table 6.1

Stationing abbreviations

Abbreviation Meaning

Abbreviation Meaning

CS

Curve to spiral

SS

Spiral to spiral

PC

Point of curvature (Tangent to curve)

ST

Spiral to tangent

PI

Point of intersection

TS

Tangent to spiral

PT

Point of tangent (Curve to tangent)

VCE

Vertical curve end

RE

Road end

VCS

Vertical curve start

RS

Road start

VPI

Vertical point of intersection

SC

Spiral to curve

XS

Cross-section

+

-

–

Enter a value. The value must be between the Start station and the End station for the road.

– to select the next station in the list. Tap Tap select the previous station in the list.

Trimble Survey Controller User Guide to

97

Page 122

6 6.4.3

Roading

Select the Offset to be Staked Out To do this: 1.

l

Do one of the following: –

Select a specific offset from a list. To do this, access the Offset field and tap . The following screen appears with a list of all offsets and their codes (if assigned):

In Key in / Template, these codes are assigned as part of the template element. In the RoadLink software, you assign a code in the template definition. –

Enter a value. A negative value for an offset to the left of the centerline; a positive value for an offset to the right. If you enter a value greater than the maximum offset in the template, a message appears. It warns that the offset is outside the range, and asks if you want to use the left sideslope, or right, depending on the value entered.

z another message appears. It warns that If you tap point positions will be in two dimensions, and asks whether you want to continue. This option is useful if you need to stake out the 2D position of a feature not defined in the template (the position of a lamppost, for example).

98

Trimble Survey Controller User Guide

Page 123

–

^

Roading

6

Tap and select an option from the Offset menu, which appears in the following screen:

Table 6-2 describes these options.

B

Table 6-2

Offset menu options

Option

Description

Leftmost

Selects the leftmost template element

Next left

Decrements the offset (selects the previous record in the list of offsets)

Next right

Increments the offset (selects the next record in the list of offsets)

Rightmost

Selects the rightmost template element

^

Tip – Select an offset from the list, or by using the . For all subsequent station values, the offset value will be updated to reflect any widening or interpolation. If you enter an offset value, that value will be maintained for all subsequent station values, even when the entered value corresponds to a value in the list.

Trimble Survey Controller User Guide

99

Page 124

6

Roading

Consider Figure 6.1. If you select offset 5 m at station 0 m, the offset value will update to follow the solid line for subsequent stations, moving from offset 5 m to offset 8 m. If you enter 5 m for the offset, the offset will follow the dashed line, maintaining offset 5 m for subsequent stations.

0m 40m

100m 8m

Figure 6.1 Offset Selection

2.

If there is a value in the Construction H.Offset field, the Construction H.Offset applied field specifies how it is applied. Do one of the following: –

To apply the offset horizontally, select Horizontal.

–

To apply the offset at the slope value of the previous template element, select Slope.

You cannot apply construction horizontal offsets at the slope value of the previous template element for points with zero offset.

10 0

Trimble Survey Controller User Guide