Browse
(440) 299-7778
Menu
(440) 299-7778
One-year parts and labor warranty30-day money-back guaranteeEnglishEspañolContact

The text of a manual · part 46 of 56

Trimble Survey Controller User Guide: Conventional Stakeout, pages 401 to 409

Pages 401 to 409 of 504, from Trimble Survey Controller User Guide

The original document is the PDF (5.9 MB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.

For the Trimble TSCe

Page 401

CHAPTER

21 21

Conventional Stakeout In this chapter: ■

Introduction

■

General procedure

Page 402

21

21.1

Conventional Stakeout

Introduction This chapter shows how to stake out points, lines, arcs, and digital terrain models (DTM) using a conventional instrument. For information about staking out a road, see Chapter 6, Roading.

C

21.2

Warning – Do not stake out points and then change the coordinate system or perform a calibration. If you do, these points will be inconsistent with the new coordinate system and with points staked out after the change.

General Procedure To stake out a point, set up the conventional instrument and complete a station setup: 1.

If necessary, change the stakeout configuration. For more information, see the next section.

2.

Define the point/line/arc/DTM. To do this, use one of the following methods:

3.

37 8

– key in data

– transfer a file from a PC

– calculate coordinates using one of the Cogo functions

Use one of the following methods to select a point: –

From the map, select the feature to be staked out - points, lines or arcs.

–

From the main menu, choose Survey / Stakeout. Then select the feature to be staked out.

Trimble Survey Controller User Guide

Page 403

Conventional Stakeout

4.

21

ã

Turn the conventional instrument to the angle indicated on the screen. If you are using a servo or robotic instrument, tap to turn the instrument to the angle indicated on the screen. Alternatively, select the Stakeout auto turn check box in the survey style.

If you are operating a robotic instrument remotely and the lock is maintained, the instrument will automatically track the prism as it moves. The stakeout graphical display will update accordingly.

m

The graphics indicate when the instrument is on line.

21.2.1

5.

. Adjust the Move the target so that it is on line and tap target distance from the instrument as indicated by the graphics, and measure again.

6.

When the graphical display indicates that the target is on the . point, tap

7.

Store the as-staked point. (This step is optional.)

8.

Repeat steps 5 and 6 until all points are staked out.

9.

End the survey.

a

Stakeout Settings You can change the default values for as-staked points, and also change how certain values are displayed during stakeout. To specify which distances are used and displayed by the Trimble Survey Controller software: 1.

From the main menu, select Configuration / Job / Cogo settings.

2.

Configure the Distances field. For example, to apply sea level (ellipsoid level) correction, select Ellipsoid.

Trimble Survey Controller User Guide

379

Page 404

21

Conventional Stakeout

To change the format: 1.

From the main menu, select Configuration / Job / Units.

2.

Configure the Stationing field. Stationing values can be displayed in the following formats: 1000.0, 10+00.00, or 1+000.0.

To change the stakeout configuration for a survey style:

f

1.

From the main menu, select Configuration / Survey Style.

2.

Highlight your conventional survey style and tap

3.

Select Stakeout. For more information about the fields that can be edited, see page 338.

o

.

To change the stakeout configuration for the current survey only:

38 0

. The following screen

1.

From the Stakeout screen, tap appears:

2.

Configure each field as required. For more information, see Stakeout, page 338.

Trimble Survey Controller User Guide

Page 405

Conventional Stakeout 21.2.2

21

Using the Graphical Display During Stakeout When staking out a point, line, arc, or road, you can use the text on the right of the screen or the graphical display on the left to navigate to the point. This section describes how to use the graphical display. In general, a solid/filled arrow means action. Use these arrows to locate the point within a certain tolerance. You can configure the tolerances for both angles and distances in the Options screen. The stakeout graphical display operates in one of two modes: Distances, or Angle and distance. To choose a mode, select Display/Deltas in the Options screen. The next section shows examples of each mode. To use the graphical display during stakeout: 1.

When you select a point to stake out, the following screen appears:

A large arrow indicates the direction in which the instrument must be turned. The screen also indicates the angle that the instrument must display.

ã to turn If you are using a servo or robotic instrument, tap the instrument to the angle indicated on the screen. Alternatively, select the Stakeout auto turn check box in the survey style.

Trimble Survey Controller User Guide

381

Page 406

21

Conventional Stakeout

If you are operating a robotic instrument remotely from the target, the graphical display is reversed and the arrows are shown from the target (prism) to the instrument. 2.

When the instrument is within the angular tolerance, the graphical display shows two hollow/outline arrows. (Use the Options screen to specify the angular tolerance.)

3.

Tap . When the distance measurement is made, a screen appears, similar to one of those shown below appears:

m

The left and right arrows are curved or straight depending on the mode selected in the Options screen: –

In the left screen, the Display/Deltas field is set to Angle and distance. The arrows are curved.

–

In the right screen, the Display/Deltas field is set to Distances. The arrows are straight.

The hollow left and right arrows show that the instrument is on line. The solid arrow indicates that the target must move away from the instrument.

38 2

Trimble Survey Controller User Guide

Page 407

4.

m

Conventional Stakeout

21

When the target has moved, tap again. If the instrument is turned off line, the two hollow arrows disappear and a solid arrow appears. The following screens show two different ways to view this:

–

In the left screen above, the Display/Deltas field is set to Angle and distance. The instrument must be turned to the left by the amount shown. When the instrument is on-line again, the two hollow arrows reappear. Direct the target on line. The up/down arrow indicates that the target must move towards the conventional instrument.

–

B

In the right screen, the Display/Deltas field is set to Distances. The target must move to the left. The instrument is then turned to follow the target. When the instrument is on line, the two hollow arrows reappear.

ã m

Tip – If you are using a servo instrument, tap back on line.

5.

When the target has moved, tap to turn the instrument again.

If the instrument is on line, two left/right hollow arrows appear. If the distance is not yet correct, a solid up/down arrow shows the direction and amount that the target must move towards or away from the instrument.

Trimble Survey Controller User Guide

383

Page 408

21

Conventional Stakeout

6.

m

Tap again. If the measurement to the target is within the angular and distance tolerances specified in the Options screen, four hollow arrows appear and the center point is filled in, as shown in the following screens:

If you are operating a robotic instrument remotely, the instrument automatically tracks the prism as it moves and continuously updates the graphical display. If a measurement to the target is within the angular and distance tolerances, tap . 7.

m

Do one of the following:

– a s s 9 y

To record the as-staked point:

If you selected the View deltas before storage check box, . The measurement and the stakeout deltas are tap displayed. Tap to store the point. If you did not select the View deltas before storage check to store the point. box, tap

–

38 4

To abandon the as-staked point without recording it, tap then . You return to the list and can stake out more points.

Trimble Survey Controller User Guide

Page 409

Conventional Stakeout 21.2.3

21

Staking Out a Point To stake out a point:

S

1.

Perform a station setup. For more information, see Chapter 19, Starting a Conventional Survey.

2.

From the map, select the point(s) to be staked out. Tap

.

If you selected more than one point from the map for staking out, the Stake out points screen appears. Proceed to the next step. If you selected one point from the map, go to step 4. 3.

A

The Stake out points screen lists all points selected for stakeout. To add more points to the list, tap to select points in the Trimble Survey Controller database or in a comma delimited (.csv, or Comma Separated Values) file. Choose the method by which points are to be selected. Use the Select from list option to select from a list of all points in the Trimble Survey Controller database. Use the Select from file option to select points in a comma delimited file. Note – If two points have the same name, only the point with the higher class - or the first point in a .csv file - is displayed.

4.

S

To select a point for stakeout, highlight the point from the Stake . out points screen and tap The following screen displays the angle to which you should turn the instrument and the distance from the instrument to the point, together with a graphical representation of this:

Trimble Survey Controller User Guide

385