For the Trimble TSCe

Page 295

CHAPTER

14 14

Calibration In this chapter: ■

Introduction

■

When to calibrate

■

Notes and recommendations

■

Performing a manual site calibration

■

Using auto calibrate

Page 296

14

14.1

Calibration

Introduction This chapter shows you how to perform both manual and automatic calibrations in the field. Before reading the chapter, you should be familiar with Chapter 2, Coordinate Systems. There is also useful information about base station coordinates in the section on Base Station Coordinates, page 224.

14.2

When to Calibrate For a GPS survey, or a survey that combines GPS measurements and conventional measurements with local control points, always complete a calibration before staking out any points, or computing offset or intersection points. For a survey that uses conventional measurements only, no calibration is required.

14.3

Notes and Recommendations

27 2

•

You can perform a calibration using one of the real-time GPS survey styles in the Trimble Survey Controller software. Do this manually, or let the Trimble Survey Controller software do it automatically. If all the points have been measured, you do not need to connect the TSCe data collector to a receiver during a manual calibration.

•

Multiple calibrations can be performed in one job. The last calibration performed and applied is used to convert the coordinates of all previously surveyed points in the database.

•

You can use up to 20 points for a calibration. Trimble strongly recommends that you use a minimum of four 3D local grid coordinates (N, E, E) and four observed WGS-84 coordinates, with the local projection and datum transformation parameters (the coordinate system). This should provide enough redundancy.

Trimble Survey Controller User Guide

Page 297

Calibration

14

Note – You can use a combination of 1D, 2D, and 3D local grid coordinates. If no projection and no datum transformation are defined, you must have at least one 2D grid point. If you did not specify the coordinate system, the Trimble Survey Controller software calculates a Transverse Mercator projection and a three-parameter datum transformation. •

Use the Trimble Geomatics Office software, Trimble’s Data Transfer utility, or ASCII transfer to transfer control points.

•

Be careful when naming points that are to be used in a calibration. Before you begin, familiarize yourself with the database search rules on page 423.

•

The set of WGS-84 coordinates must be independent of the set of grid coordinates.

•

You select the grid coordinates. Select the vertical coordinates (elevation), the horizontal coordinates (northing and easting values), or all of these together.

•

Place the calibration points around the perimeter of the site. Do not survey outside of the area enclosed by the calibration points, as the calibration is not valid beyond this perimeter.

•

The origin of the horizontal adjustment in a calibration is the centroid of the measured calibration points. The origin of the vertical adjustment is the first point in the calibration with an elevation.

•

When reviewing a calibration point in the database, notice that the WGS-84 values are the measured coordinates. The grid values are derived from these, using the current calibration. The original keyed-in coordinates remain unchanged. (They are stored elsewhere in the database as a point with the Type field showing Keyed in coordinates and the Stored as field showing Grid.)

Trimble Survey Controller User Guide

273

Page 298

14

14.4

Calibration

•

When you are calibrating a no projection, no datum job, (where ground coordinates are required after calibration) you must define the project height (average site height). When the job is calibrated, the project height is used to compute a ground scale factor for the projection, using the inverse of the ellipsoid correction.

•

When you have calibrated a scale-only job, the scale factor that you specified in the job is used as the scale factor in the projection.

Performing a Manual Site Calibration To calibrate a survey manually: 1.

Key in, transfer, or use a conventional instrument to measure the grid coordinates of the control (calibration) points.

2.

Check or enter the calibration tolerances. For more information, see Site Calibration, page 210.

3.

Use GPS to measure the control points.

4.

Name or select the pairs of points to be used for the calibration. A pair of points consists of the grid coordinates and the WGS-84 coordinates for the same point.

5.

Perform the calibration.

6.

Check residuals, and recalibrate if necessary.

7.

Apply the calibration.

Note – Before starting a manual calibration, read Notes and Recommendations, page 272. The following steps describe how to select the points for a calibration and then perform the calibration using the Trimble Survey Controller software. Do this once you have entered grid coordinates, checked the settings in the Survey Style, and measured the points using GPS.

27 4

Trimble Survey Controller User Guide

Page 299

Calibration

14

1.

From the main menu, choose Survey. Select a real-time survey style.

2.

From the Survey menu, choose Site calibration. The Site calibration screen appears.

3.

Tap

4.

Enter the name of the grid point. To do this, highlight the Grid point field and tap . Select a point that you have keyed in, transferred, or measured using a conventional instrument. Do the same for the GPS point field. The two point names do not have to be the same, but they should correspond to the same physical point.

A

. The following screen appears:

l

In the Use field, choose whether to use the vertical coordinate of the grid point, the horizontal coordinates, or both horizontal and vertical coordinates. 5.

Tap

E

. The following screen appears:

Trimble Survey Controller User Guide

275

Page 300

14

Calibration

W

The residuals for each point are not displayed until at least three 3D points are included in the calibration to provide redundancy.

14.4.1

6.

to see the horizontal and vertical shifts that the Tap calibration has calculated. The following screen appears:

7.

To add more points, tap

8.

Repeat steps 3 through 6 until all the points are added.

9.

Do one of the following:

9 to return to the calibration screen.

@ to store the

–

If the residuals are acceptable, tap calibration.

–

If the residuals are not acceptable, recalculate the calibration.

Recalculating a Calibration Recalculate a calibration if the residuals are not acceptable, or if you want to add or delete points. Recalculate using one of the following:

27 6

• some of the points

• only the horizontal component of a point

• only the vertical component of a point

Trimble Survey Controller User Guide

Page 301

Calibration

14

To recalculate a calibration: 1.

From the main menu, select Survey. Then select a real-time survey style.

2.

From the Survey menu, choose Site calibration.

3.

Do one of the following: – – –

4.

Tap d A f @

To remove (exclude) a point, highlight the point name and . tap

To add a point, tap on page 275.

. For more information, see step 4

To change the components used for a point, highlight the . In the Use field, choose whether point name and tap to use the vertical coordinate of the grid point, the horizontal coordinates, or both horizontal and vertical coordinates. to apply the new calibration.

Note – Each calibration calculation is independent of the previous one. When a new calibration is applied, it overwrites any previously calculated calibration.

14.5

Using Auto Calibrate A calibration calculates the parameters needed to convert the GPS-measured coordinates into local grid coordinates. During an RTK survey, the Trimble Survey Controller software does this automatically. When you use the auto calibrate function, it automatically computes and stores a calibration every time a calibration point is measured. To calibrate a survey automatically: 1.

Key in, transfer, or use a conventional instrument to measure the grid coordinates of the local control points.

2.

Select the Auto calibrate check box. Trimble Survey Controller User Guide

277

Page 302

14

Calibration

3.

Use GPS to measure the calibration points.

The first three steps complete the automatic calibration. The following steps are optional: 1.

Inspect the calibration results.

2.

Change the results if they are unsatisfactory.

Note – Carry out the complete calibration before staking out any points, computing offset and/or intersection points, or computing a resection from GPS points.

14.5.1

Keying In Grid Coordinates To key in grid coordinates: From the main menu, select Key in / Points. The Point screen appears.

2.

Enter the point name in the Point name field. Tap

3.

Enter details or features of the point in the Code field. . Tap

4.

In the Method field, select Coordinates. Check that the coordinate fields are North, East, and Elevation. If they are not, and change the Coordinate view to Grid. Key in the tap known grid coordinates and tap .

5.

Select the Control point check box. (This ensures that the point is not overwritten by a measured point.)

6.

27 8

E

1.

E o

9

.

E

Repeat steps 2 and 3 for all grid coordinate points. Then tap to return to the main menu.

Trimble Survey Controller User Guide

Page 303

Calibration 14.5.2

14

Transferring Grid Coordinates Transfer coordinates using the Trimble Geomatics Office software, the Data Transfer utility, or ASCII transfer. For more information, see Data Transfer between the TSCe Data Collector and the Office Computer, page 68. Make sure that these coordinates are:

14.5.3

• transferred as grid coordinates (N, E, E), not as WGS-84 coordinates (L, L, H)

• control class points

Using a Conventional Instrument to Measure Grid Points For information, see Station Setup, page 345.

14.5.4

Selecting Automatic Calibration To select Auto calibrate:

14.5.5 f

1.

From the main menu, choose Configuration / Survey Styles. The Survey Styles menu appears.

2.

Highlight your RTK survey style and tap

3.

Select Site calibration. The Site calibration screen appears.

4.

Select the Auto calibrate check box. For more information on changing the calibration tolerances, see Site Calibration, to accept the screen. The menu for the page 210. Tap selected survey style appears.

5.

Tap s

.

E to accept the changes and return to the main menu.

Using GPS to Measure Calibration Points Use GPS to survey the points. The Trimble Survey Controller software automatically matches the grid points to the WGS-84 values and then calculates, stores, and applies the calibration. Trimble Survey Controller User Guide

279

Page 304

14

Calibration f

When one point has been calibrated, or a projection and datum transformation have been defined, the softkey appears. You can use this to navigate to the next point. As you measure another calibration point, the new calibration is calculated, stored, and applied to the job. To measure a calibration point:

B

1.

From the main menu, choose Survey.

2.

Highlight your RTK survey style and select Measure points. The Measure points screen appears.

3.

In the Method field, select Calibration point.

4.

. A list of Access the Grid point name field and tap keyed-in grid coordinates appears. Highlight the point to be measured and tap . The point name is inserted into the Grid point name field.

k l

E s

Tip – If you have not yet keyed in the grid coordinates for this point, tap while the cursor is in the Point name field. The Point screen appears. Enter the coordinates and then tap .

The Trimble Survey Controller software enters the GPS point name according to the selected Site calibration / Calibration point name option in the survey style.

m

5.

Enter values for the Code and Antenna height fields.

6.

When the antenna is centered and vertical over the control . The data collector starts to record data. point, tap s

Keep the antenna vertical and stationary while data is recorded. 7.

When the preset required time has elapsed, and the precisions to store the point. are satisfactory, tap The calculations are then done automatically and the results are stored.

28 0

Trimble Survey Controller User Guide

Page 305

Calibration

14

Note – When the Trimble Survey Controller software is performing an automatic calibration, the results of the calibration are not normally displayed. However, if a calibration exceeds the tolerances that have been set, the residuals are displayed. For more information, see the next section. 8.

f

Enter the next calibration point name in the Point name field and tap . The graphical display screen appears, with the azimuth and distance to the next point displayed on the right. To use the arrow display, start moving forward with the data collector held in front of you as normal. The arrow points in the direction of the next calibration point. Walk towards the point. About 10 feet (3 meters) from the point, the arrow disappears and the point is displayed. For more information, see Using the Graphical Display to Navigate, page 310. When the point is located, tap

9.

14.5.6

9

.

Repeat steps 4 through 8 until all the calibration points are measured.

If Calibration Tolerances Are Exceeded The calibration residuals are only displayed if the calibration tolerances are exceeded, as shown in the following screen:

Trimble Survey Controller User Guide

281

Page 306

14

Calibration

If this happens, consider removing the point with the most extreme residuals. Do one of the following: •

If at least four points are left after removing that point, recalibrate using the remaining points.

•

If not enough points are left after removing that point, measure it again and recalibrate.

EE

It may be necessary to remove (re-measure) more than one point. To remove a point from the calibration calculations:

14.5.7

.

1.

Highlight the point name and tap

2.

In the Use field, select Off and tap . The calibration is recalculated and the new residuals are displayed.

3.

Tap

@ to accept the calibration.

Inspecting the Results of an Automatic Calibration To view the results of an automatic calibration:

14.5.8

W

1.

From the Survey menu, choose Site calibration. The Site calibration screen appears.

2.

to see the Calibration results screen. For more Tap information, see Calibration Results screen on page 276.

Changing the Results of an Automatic Calibration To change a calibration that has been calculated using the Auto calibrate function, select Site calibration from the Survey menu. Then proceed as described in Performing a Manual Site Calibration, page 274.

28 2

Trimble Survey Controller User Guide