Page 83

Job Operations Table 3-4

3

Coordinate view options (Continued)

Option

Description

Az HD VD

View as azimuth, horizontal distance, and vertical distance

HA HD VD

View as horizontal angle, horizontal distance, and vertical distance

∆ Grid

View as differences in Northing, Easting, and Elevation from the instrument point

Note – If the coordinate value for a point is “?”, it is possible that the point is stored as a GPS point but the Coordinate view field is set to Local or Grid, and you have not defined a datum transformation and projection. Change the Coordinate view setting to WGS-84, define a datum transformation and/or projection, or calibrate the job. Alternatively, it is possible that the point is stored as a polar vector from another point but that source point is deleted. Undelete it. –

The grade of a slope can be displayed in one of the following formats: angle, percent, or ratio. The ratio can be displayed as Rise:Run or Run:Rise. Figure 3.1 illustrates these.

p Slo e

Rise

Run

Figure 3.1 Rise and run in the grade display

Trimble Survey Controller User Guide

59

Page 84

3

Job Operations

The setting in the Laser VA display field determines whether the laser measurements are displayed as vertical angles measured from the zenith, or inclinations measured from horizontal. Use the HA VA angle display field to specify how horizontal and vertical angles are displayed.

4.

3.8

Tap

\ to accept the settings and return to the Job menu.

System Settings and Corrections Various settings and corrections affect how data and results are displayed on the TSCe data collector. It is important to understand the effects of the settings used. Note – If you change the settings in a subsequent job, the original job retains its settings. When you change a setting, a note is recorded in the job database.

60

Trimble Survey Controller User Guide

Page 85

Job Operations 3.8.1

3

Cogo Settings Screen To access the list of settings and corrections, select Configuration from the main menu. Then select Job / Cogo settings. The following screen appears:

Change these settings as required. They are applied to the current job (if one is open) or to the next job that you create.

3.8.2

Options Softkey o

When you select Cogo from the main menu, an softkey appears in some of the screens. This softkey lets you change certain settings or corrections. Note – Parameters that are set in the Options screen only apply to the current job. Different jobs can have different settings. 3.8.3

Distance Display The Distances field defines how distances are displayed and which distances are used for calculations in the Trimble Survey Controller software. Select one of the following options: • Ground (the default setting) • Ellipsoid • Grid Trimble Survey Controller User Guide

61

Page 86

3

Job Operations

Figure 3.2 shows the options between points A and B.

B Ground distance

A Grid distance Ellipsoid distance Ellipsoid Figure 3.2

Distances used by the Trimble Survey Controller software between points A and B

Note – Distance and height/elevation fields have the suffix (grnd), (ell), or (grid), depending on the value in the Distances field. Ground distance A ground distance is the horizontal distance calculated between the two points at the mean elevation parallel to the chosen ellipsoid. If an ellipsoid has been defined in the job and the Distances field is set to Ground, the distance is calculated parallel to that. If no ellipsoid has been defined, the WGS-84 ellipsoid is used. Ellipsoid distance If the Distances field is set to Ellipsoid then a correction is applied and all distances are calculated as if on the local ellipsoid, which usually approximates to sea level. If no ellipsoid has been specified, the WGS-84 ellipsoid is used. Note – If the coordinate system for a job is defined as Scale factor only, ellipsoid distances cannot be displayed. 62

Trimble Survey Controller User Guide

Page 87

Job Operations

3

Grid distance If the Distances field is set to Grid, the grid distance between two points is displayed. This is the simple trigonometrical distance between the two sets of two-dimensional coordinates. If the coordinate system for the job is defined as Scale factor only, and the Distances field is set to Grid, the Trimble Survey Controller software displays ground distances multiplied by the scale factor. Note – A grid distance between two measured GPS points cannot be displayed unless you have specified a datum transformation and a projection, or performed a site calibration.

3.8.4

Curvature Correction In the Trimble Survey Controller system, all ellipsoid and ground distances are parallel to the ellipsoid.

3.8.5

Azimuth Display The azimuth displayed and used by the Trimble Survey Controller software depends on the coordinate system that you defined for the current job: •

If you defined both a datum transformation and a projection, or if you selected Scale factor only, the grid azimuth is displayed.

•

If you defined no datum transformation and/or no projection, the best available azimuth is displayed. A grid azimuth is the first choice, then a local ellipsoidal azimuth, then the WGS-84 ellipsoid azimuth.

•

If you are using a laser rangefinder, the magnetic azimuth is displayed.

In the Survey / Offsets screen you can select which azimuth is used. For more information, see Azimuth plus angle, page 165. The azimuth that the Trimble Survey Controller software uses is identified by the suffix (grid), (local), (WGS84), or (mag). Trimble Survey Controller User Guide

63

Page 88

3 3.8.6

Job Operations

South Azimuth If a south azimuth display is required, set the South azimuth field to Yes. All azimuths still increase clockwise. Figure 3.3 shows the effect of setting the South azimuth fields to No or Yes. N

N

0

180

270

90

270

180

0

S

S

South azimuth = No

South azimuth = Yes

Figure 3.3

3.8.7

90

South azimuth setting

Grid Coordinates Use the Grid coords field to set the grid coordinates to increase in one of the following sets of directions:

64

• north and east

• south and west

• north and west

• south and east

Trimble Survey Controller User Guide

Page 89

Job Operations

3

Figure 3.4 shows the effect of each setting. N

N

(–50,–50)

(50,50)

(–50,–50)

(50,50)

S

S Increase South-West

Increase North-East

N

N (–50,–50)

(50,50)

(–50,–50)

(50,50) S Increase South-East

S Increase North-West

Figure 3.4

3.8.8

Grid coordinates setting

Magnetic Declination Set the magnetic declination for the local area if magnetic bearings are being used in the Trimble Survey Controller software. You can use magnetic bearings if you choose the Brng-dist from a point method in the Survey/Offsets screen.

Trimble Survey Controller User Guide

65

Page 90

3

Job Operations

Enter a negative value if magnetic north is west of true north. Enter a positive value if magnetic north is east of true north. For example, if the compass needle points 7° to the east of grid north, the declination is +7° or 7°E. Note – Use the published declination values if available.

3.8.9

Subdivide Pts Code When you subdivide a line or arc, a number of points are created. Use the Subdivide pts code field to specify the code that the new points will be allocated. Choose from the name or the code of the line or arc that is to be subdivided.

3.8.10

Project Height The project height can be defined as part of the coordinate system definition. To find it, select Configuration / Job / Coordinate System in either the Library or Key in / Projection dialogs. If a point has no elevation, the Trimble Survey Controller software uses the project height for Cogo calculations. If you combine GPS and 2D conventional observations, set the Project height field to approximate the height of the site. This height is used with 2D points to calculate grid and ellipsoid distances from measured ground distances. If you have defined a projection and you intend to do a 2D survey, you must enter a value for the project height. This reduces measured ground distances to ellipsoid distances. If you edit the project height (or any other local site parameter) after calibrating, the calibration becomes invalid and must be reapplied.

66

Trimble Survey Controller User Guide