The text of a manual · part 61 of 83
Trimble Survey Controller Reference Manual: Using Conventional Instruments, pages 543 to 550
Pages 543 to 550 of 744, from Trimble Survey Controller Reference Manual
The original document is the PDF (8.5 MB). This is its text as extracted, unedited; tables and drawings read best in the PDF, and each page heading opens it at that page.
For the Trimble TSC1
Page 543
Using Conventional Instruments
19
8.
Use the graphical display screen, or the text display, to navigate the target to the point, as shown in Figure 19.32. For more information, see Using the Graphical Display During Stakeout, page 504.
9.
When all arrows are hollow, mark the point. Do one of the following: – z s s y
If you want to record the as-staked point:
If the View deltas before storage field is set to Yes, press . The measurement and the stakeout deltas are displayed. Press to store the point.
If the View deltas before storage field is set to No, press to store the point. –
19.7.5
=
If you do not want to record the as-staked point, press then . You return to the list and can stake out more points.
Staking Out a Line To stake out a line: 1.
From the main menu, select Survey. From the Select Survey Style menu, select your Conventional Survey Style.
2.
Select Station Setup and perform a station setup.
3.
Select Stakeout / Lines. The Survey/Stakeout/Line screen appears.
4.
In the Line name field, enter the name of the line to be staked out. Do one of the following:
5.
l k
– to display a list of lines stored in the Trimble Press Survey Controller software database. Highlight the required line and press .
–
Press
\ and define the line to be staked out.
Enter a value in the Target height field. Trimble Survey Controller Reference Manual Volume 2
511
Page 544
19
Using Conventional Instruments
6.
Choose a setting for the Stake to Field. For more information, see Stake to options, page 514.
x
Other fields appear, depending on what you choose. Fill in the information required.
51 2 m
7.
. The TSC1 data collector displays a large arrow that Press indicates the direction in which you must turn the instrument.
8.
When the target is on line with the instrument, press . There are values in the following fields, if they are appropriate to the stakeout method used: –
H. Dist reqd – the horizontal distance from the instrument to the line or station on the line.
–
H. Ang reqd – the horizontal angle reading that should appear on the instrument to point in the direction of the line or station on the line.
–
Delta H. Ang – the angle that the instrument needs to turn to point in the direction of the line or station on the line.
–
Go In/Out – the horizontal distance along the instrument line of sight, to the line or station on the line.
–
Go Left/Right – the horizontal distance perpendicular to the instrument line of sight, to the line of station on the line.
–
V. Dist (cut/fill) – the vertical distance between the target position and the point on the line to be staked out.
–
Stationing – the station/chainage of the target position perpendicular to the line.
–
∆ Station – the difference in the stationing between the target position and the station to be staked out. A positive value means that the station to be staked out is towards the beginning of the line. A negative value means that the station to be staked out is towards the end of the line.
–
H.Offset – the offset of the target position in relation to the line. A positive value is an offset to the right and a negative offset is an offset to the left.
Trimble Survey Controller Reference Manual Volume 2
Page 545
Using Conventional Instruments
– 9.
19
Grade to line – the grade of the slope between the target position and the closest point on the line.
Use the graphical display or the text display to navigate the target to the point, as shown in Figure 19.33. For more information, see Using the Graphical Display During Stakeout, page 504.
Figure 19.33 Graphical display screen – navigate to line
10. When all four arrows are hollow, mark the point. Do one of the following: – z s s y- +
If you want to record the as-staked point:
If the View deltas before storage field is set to Yes, press . The measurement and the stakeout deltas are displayed. Press to store the point.
If the View deltas before storage field is set to No, press to store the point. –
=
If you do not want to record the as-staked point, press then . You return to the Survey/Stakeout/Line screen. Press or to select the next station on the line, and stake out the points as described above.
Trimble Survey Controller Reference Manual Volume 2
513
Page 546
19
Using Conventional Instruments
Stake to options When staking out a line, the options for the Stake to field are: •
Station on the line – with this, also enter the station to be staked out.
•
Station/offset from line – with this, also enter the station to be staked out, a horizontal offset, and a vertical offset.
•
Slope from line – with this, also enter the slope parameters for a slope to the left and/or right of the line as required.
For more information about these options, see Stake To Options, page 414.
19.7.6
Staking Out a Curve To stake out a curve: 1.
From the main menu, select Survey. From the Select Survey Style menu, select your Conventional Survey Style.
2.
Select Station Setup and perform a station setup.
3.
Select Stakeout / Curves. The Survey/Stakeout/Curve screen appears.
4.
In the Curve name field, enter the name of the curve to be staked out. Do one of the following:
l k
– to display a list of curves stored in the Trimble Press Survey Controller software database. Highlight the required curve and press .
–
Press
\ and define the curve to be staked out.
5.
Enter a value in the Target height field.
6.
Choose a setting in the Stake to field. For more information, see Stake to options, page 516. Other fields appear, depending on what you choose. Fill in the information required.
51 4
Trimble Survey Controller Reference Manual Volume 2
Page 547
x
Using Conventional Instruments m
19
7.
Press . The TSC1 data collector displays a large arrow that indicates the direction in which you must turn the instrument.
8.
When the target is on line with the instrument, press
.
There are values in the following fields, if they are appropriate to the stakeout method used: –
H. Dist reqd – the horizontal distance from the instrument to the curve or station on the curve.
–
H. Ang reqd – the horizontal angle reading that should appear on the instrument to point in the direction of the curve or station on the curve.
–
Delta H. Ang – the angle that the instrument needs to turn to point in the direction of the curve or station on the curve.
–
Go In/Out – the horizontal distance along the instrument line of sight, to the curve or station on the curve.
–
Go Left/Right – the horizontal distance, perpendicular to the instrument line of sight, to the curve of station on the curve.
–
V. Dist (cut/fill) – the vertical distance between the target position and the point on the curve to be staked out.
–
Stationing – the station/chainage of the target position, perpendicular to the curve.
–
∆ Station – the difference in the stationing between the target position and the station to be staked out. A positive value means that the station to be staked out is towards the beginning of the curve. A negative value means that the station to be staked out is towards the end of the curve.
–
H.Offset – the offset of the target position in relation to the curve. A positive value is an offset to the right and a negative offset is an offset to the left.
–
Grade to curve – the grade of the slope between the target position and the closest point on the curve.
Trimble Survey Controller Reference Manual Volume 2
515
Page 548
19
Using Conventional Instruments
9.
Use the graphical screen display or the text display to navigate the target to the point, as shown in Figure 19.34. For more information, see Using the Graphical Display During Stakeout, page 504.
Figure 19.34 Graphical display screen – navigate to curve
10. When all four arrows are hollow, mark the point. Do one of the following: – z s s y-+
If you want to record the as-staked point:
If the View deltas before storage field is set to Yes, press . The measurement and the stakeout deltas are displayed. Press to store the point.
If the View deltas before storage field is set to No, press to store the point. –
Stake to options When staking out a curve, the options for the Stake to field are: •
51 6
=
If you do not want to record the as-staked point, press then . You return to the Survey/Stakeout/Curve screen. Press or to select the next station on the curve, then stake out the points as described above.
Station on the curve – with this, also enter the station to be staked out.
Trimble Survey Controller Reference Manual Volume 2
Page 549
Using Conventional Instruments
19
•
Station/offset from curve – with this, also enter the station to be staked out and any horizontal and vertical offset.
•
Slope from curve – with this, also enter the slope parameters for a slope to the left and/or right of the curve, as required.
•
Intersect point of curve.
•
Center point of curve.
For more information about these options, see Stake To Options, page 414.
19.7.7
Staking Out a DTM To stake out a digital terrain model (DTM): 1.
From the main menu, select Survey. From the Select Survey Style menu, choose your Conventional Survey Style.
2.
Select Station Setup and perform a station setup.
3.
Select Stakeout / DTMs. The Survey/Stakeout/DTM screen appears.
4.
In the DTM field, select the terrain model to be staked out.
5.
Enter a value in the Target height field and, if applicable, the V.Offset field.
6.
Press
7.
When the graphical display screen appears, press x
.
m
.
The screen displays the coordinates of the current position and the vertical distance above (cut) or below (fill) the DTM. 8.
Do one of the following: – z
If you want to record the point:
s
If the View deltas before storage field is set to Yes, press . The measurement and the stakeout deltas are displayed. Press to store the point.
Trimble Survey Controller Reference Manual Volume 2
517
Page 550
19
Using Conventional Instruments s y=
If the View deltas before storage field is set to No, press to store the point. The Trimble Survey Controller software stores the point and the stakeout deltas. – 9.
19.7.8
= then If you do not want to record the point, press . You return to the list and can stake out more points.
Press to return to the Survey/Stakeout/DTM screen.
Staking Out a Road To stake out a road using a conventional instrument, use the graphical screen shown in Using the Graphical Display During Stakeout, page 504. For more information about staking out a road, see Chapter 18, Roading.
19.8
Ending a Conventional Survey If a survey is running, end it before editing the current Survey Style or changing Survey Styles. You must also end the survey before accessing job functions such as copying a job (see Copying a Job, page 91). To end a survey, select End survey from the Survey menu. If you are operating a robotic instrument remotely, the instrument can be powered down from the remote end (target) once End survey is selected.
C
51 8
Warning – The current station setup is lost when you select End Survey.
Trimble Survey Controller Reference Manual Volume 2