Page 65
CHAPTER
3 3
Job Operations In this chapter: ■
Introduction
■
Job management
■
Reviewing the job database
■
Map of current job
■
Status of current job
■
Selecting comma delimited (.csv) files
■
System units
■
System settings and corrections
Page 66
3
Job Operations
3.1
Introduction Before starting a survey, select or create a job. All subsequent settings and data are stored in this job. Note – In the Trimble Survey Controller software, GPS and conventional data can be combined in a single job. You can change certain settings (such as the units and distance display) at any time. Trimble recommends that you set these before creating a job, as this reduces the number of records in the job database. For more information, see System Settings and Corrections, page 60.
3.2
Job Management You can create, open, copy, delete, and close jobs in the Trimble Survey Controller database. The current job name is displayed at the top of the main menu. In addition, tap and hold on the title bar in the current screen to display a ToolTip of the job name. To perform most job operations, select Files from the main menu. Then select Job management.
3.2.1
Creating a Job n
To create a job: 1.
Tap
.
The New job screen appears.
42
E
2.
Enter the job name in the Name field.
3.
In the Select coordinate system field, select a coordinate system . option. See Selecting a Coordinate System, below. Tap
Trimble Survey Controller User Guide
Page 67
Job Operations 3.2.2
3
Selecting a Coordinate System When you create a job, select a coordinate system using one of the following options: •
Select from library
•
Key in parameters
•
Scale factor only
•
Copy from other job
•
No projection/no datum
If a survey is to contain conventional observations only, select Scale factor only. If conventional observations are to be combined with GPS measurements, choose a coordinate system now. For more information, see Choosing a Coordinate System for a GPS Survey, page 38. If you are not sure of the coordinate system, select No projection/no datum. You can define the values later in the job and then all points will be updated. (To do this, select Configuration / Job / Coordinate or and enter the parameters or select a system. Tap coordinate system.)
kÌ
Note – If you are using GPS, define the coordinate system and/or calibration for the job before computing offsets and/or intersection points, or staking out points. If you later change the coordinate system or calibration, any of the above points that are already computed, measured, or staked out will be inconsistent with the new coordinate system, and any points computed or staked out after the change. Select from library To select a coordinate system and zone from the list provided by the Trimble Survey Controller software:
E
1.
In the New job dialog, choose the Select from library option.
2.
Tap
. The Select coordinate system screen appears. Trimble Survey Controller User Guide
43
Page 68
3
Job Operations
3.
Select the appropriate coordinate system and zone for the area.
4.
To use a geoid file from the database, select the Use geoid model check box and set the Geoid model field to the geoid file name. For more information, see Using a Geoid Model, page 34.
5.
To use a datum grid file from the database, select the Use datum grid check box and set the Datum grid field to the datum grid file name. For more information, see Using a Datum Grid File, page 32.
6.
To use ground coordinates for the job, select an option from the Coordinates field and complete the fields below as required. For more information, see Working with Ground Coordinates, page 36.
7.
The project height is used with 2D points to reduce ground distances in Cogo calculations. For more information, see Project Height, page 66.
Key in parameters
E
To key in the projection and datum transformation parameters for the site: 1.
In the New job screen, choose Key in parameters. Tap The Key in parameters screen appears.
44
.
2.
Select Projection, and enter the details for the site.
3.
To use ground coordinates for the job, select an option from the Coordinates field and complete the fields as required. For more information, see Working with Ground Coordinates, page 36.
4.
The project height is used with 2D points to reduce ground distances in Cogo calculations. For more information, see Project Height, page 66.
5.
Select Datum transformation, and enter the appropriate parameters.
Trimble Survey Controller User Guide
Page 69
Job Operations
3
Note – When keying in the coordinate system parameters, define the local ellipsoid in either the Projection screen or the Datum transformation screen. If the values change in one of these screens, the Trimble Survey Controller software automatically changes them in the other. The source ellipsoid is always WGS-84. The parameters do not appear here and there is no need to edit them. Scale factor only To select a Scale factor only coordinate system: 1.
In the New job screen, choose Scale factor only. Tap The Projection screen appears.
2.
E
.
Enter a value in the Scale factor field.
All distances measured with a conventional instrument are scaled by this value. Copy from other job To copy a coordinate system from another job in the database: 1.
In the New job screen, choose Copy from other job. Tap
2.
Select the job name that you want to copy from.
E
.
No projection/no datum
E
To select a coordinate system with an undefined projection and datum: 1. 2.
In the New job screen, choose No projection/no datum. Tap . The No projection/no datum screen appears.
Set the Coordinates field to Ground, and enter a value (average site height) in the Project height field to use ground coordinates after a site calibration. Alternatively, set the Coordinates field to Grid.
Trimble Survey Controller User Guide
45
Page 70
3
Job Operations
3.
Select the Use geoid model check box, and select a geoid model to calculate a Geoid/Inclined plane vertical adjustment after a site calibration.
Any points measured using GPS are displayed only as WGS-84 coordinates. Any points measured using a conventional instrument are displayed with null (?) coordinates.
3.2.3
Opening a Job To open a job, highlight the name of the required job and tap
3.2.4
Y
E
.
Copying a Job
E
To copy a job, highlight the name of the job to be copied and tap . Enter a name for the new job in the To name field and tap complete job is copied.
B 3.2.5
. The
Tip – Use Windows Explorer to rename a file.
Copying between Jobs Use this option to copy data between jobs. You can copy the following data: • • • • •
46
Calibration All control points Calibration and control points Roads Points
Trimble Survey Controller User Guide
Page 71
Job Operations
3
To copy data from another job: 1.
From the main menu, select Files / Copy between jobs.
2.
In the Job to copy from field, select the name of the job that contains the data you want to copy.
3.
In the Job to copy to field, select the name of the job that you want to copy the data into.
4.
In the Copy field, select the appropriate option for the data that you want to copy.
5.
If you want to copy a point, select the Copy duplicate points check box, even if the point already exists in the job that you are copying to. If you select the Copy duplicate points check box, the Overwrite check box appears. Select this if you want the duplicate points you copy to overwrite (delete) the points in the . job you are copying to. Tap
E
When copying points, if the two jobs have different calibrations, the following message appears:
yz
Calibrations differ. Copy calibration?
6.
Tap or as appropriate. If you tap calibration is also copied.
y the
If duplicate points were copied, a warning message appears to show how many duplicates were copied.
3.3
Reviewing the Job Database To review the database for the current job, see Reviewing the Database, page 15.
Trimble Survey Controller User Guide
47
Page 72
3
Job Operations
3.4
Map of Current Job The Map of current job screen is a graphical representation of the features (points, lines, arcs) in the job database. You can move around the map, hide or display different parts of the map, and select features for common tasks. You can also display a background map.
L
To access the Map of current job screen, do one of the following: .
•
Tap
•
From the main menu, select Files / Map of current job.
A screen, similar to the following one, appears:
Different symbols identify different point types. The current position of the GPS antenna is shown as a vertical/horizontal cross ( ). The current orientation of a conventional instrument is shown by a dotted line extending from the instrument to the end of the screen, or to the prism when a distance is measured. The location of the prism is shown as a cross ( ). If there is a point with the same name as another point in the database, the point with the higher search class is displayed. For more information about how the Trimble Survey Controller software uses search classes, see Appendix B, Database Search Rules. Note – Only grid coordinates are displayed. If you have not defined a projection, only points stored as grid coordinates appear. 48
Trimble Survey Controller User Guide
Page 73
Job Operations
3
Note – If the Grid coords field in the Cogo settings screen is set to Increase South–West or Increase South–East, this screen is rotated by 180°. The letter N on the north arrow denotes Grid 0°. Table 3.1 describes the map softkeys that you can use to navigate around the map or to change the map display options. The effect on tapping on the map depends on the active softkey selected. When no softkey is selected, the map is in Select mode. For more information on selecting features from the map, see Selecting Features, page 51. Table 3.1
Softkeys in map of current job screen
Softkey
Function
N O ( P #Q
Tap the softkey to zoom in to the center of the map area. Tap and hold on the softkey to make it active. Tap on an area of the map to zoom in to, or drag a box around the area you want to view. Tap the softkey again to deselect it. Tap the softkey to zoom out from the center of the map area. Tap and hold on the softkey to make it active. Tap on area of the map to zoom out from. Tap the softkey again to deselect it. Shifts the center of the map area to another part of the map. Tap on a part of the map to center the area, or tap and drag the map area to where you want to pan. Zooms to extents - shows all features on the screen. Displays the other softkeys (see below). Shows a legend for the feature symbols and lets you choose which features to display. Place a check mark against the features you want displayed.
Trimble Survey Controller User Guide