Page 445

GPS Stakeout

6.

17

–

H. Dist – the horizontal distance between the present position and the point on the curve to be staked out

–

V. Dist (cut/fill) – the vertical distance between the present position and the point on the curve to be staked out

–

Stationing – the station/chainage of the present position

–

∆ Station – the difference in stationing between the present position and the station to be staked out. A positive value means that the station is towards the beginning of the curve. A negative value means that the station is towards the end of the curve.

–

Offset (left/right) – the offset of the present position in relation to the line. A positive value is an offset to the right and a negative offset is an offset to the left.

–

Grade to curve – the grade of the slope between the present position and the closest point on the curve

Use the graphical display or the text display (see Figure 17.14) to navigate to the point. For more information, see Using the Graphical Display to Navigate, page 400.

F

Figure 17.14 Staking out a curve

7.

Closer to the point, press to go into Fine mode.

8.

When the two symbols coincide, check the precisions and mark the point.

Trimble Survey Controller Reference Manual Volume 2

413

Page 446

17

GPS Stakeout

9.

10. Press press

17.8.1 m

To record the as-staked point, press . The Trimble Survey Controller software measures the point.

-= + to return to the Survey/Stakeout/Curve screen. Then or to select the next station on the curve.

Stake To Options When staking out a curve, the options for the Stake to field are:

17.8.2

•

To the curve

•

Station on the curve – with this, also enter the station to be staked out

•

Station/offset from curve – with this, also enter the station to be staked out and any horizontal and vertical offset

•

Slope from curve – with this, also enter the slope parameters for a slope to the left and/or right of the curve, as required

•

Intersect point of curve

•

Center point of curve

To the Curve Select the To the curve option to stake out points on a curve, starting at the closest point (1) to your current position (2). If your current position is beyond the end of the curve, the Trimble Survey Controller software directs you to the closest point along the extension of the curve.

41 4

Trimble Survey Controller Reference Manual Volume 2

Page 447

GPS Stakeout

17

Figure 17.15 shows the text screen and a graphical representation of this option.

2 1

Figure 17.15 Stake to the curve

17.8.3

Station on the Curve Select the Station on the curve option to stake out stations (1) on a curve with a defined station increment (2). Figure 17.16 shows the text screen and a graphical representation of this option.

2

1

Figure 17.16 Stake to station on the curve

Trimble Survey Controller Reference Manual Volume 2

415

Page 448

17 17.8.4

GPS Stakeout

Station/Offset from Curve Select the Station/offset from curve option to stake out points (1) perpendicular to stations (3) on the defined curve (2) and offset to the right or left by a certain distance (4). Figure 17.17 shows the text screen and a graphical representation of this option.

4

2 1 3

Figure 17.17 Stake to station/offset from curve

17.8.5

Slope from Curve Select the Slope from curve option to stake out points at any position on a surface made up of sloping lines (2), at defined grades (3), perpendicular to the defined curve (cross-section = (1)). Different slopes can be defined on the left and the right of the curve. At any point offset from the curve the value for cut (4) or fill (5) is displayed.

41 6

Trimble Survey Controller Reference Manual Volume 2

Page 449

GPS Stakeout

17

Figure 17.18 shows the text screen and a graphical representation of this option.

2

3

2

1

4

3 5

Figure 17.18 Stake to slope from curve

The left side of the curve is the side on your left when looking along the curve in the direction of increasing stationing. Use the Slope left field and the Slope right field to define the type of grade in one of the following ways: •

Horizontal and vertical distance

•

Grade and slope distance

•

Grade and horizontal distance

You can also enter a value in the Grade field (this is optional).

Trimble Survey Controller Reference Manual Volume 2

417

Page 450

17 17.8.6

GPS Stakeout

Intersect Point of Curve Select the Intersect point of curve option to stake out the intersection point (1) of a defined curve (2). Figure 17.19 shows the text screen and a graphical representation of this option.

1

2

Figure 17.19 Stake to intersect point of curve

17.8.7

Center Point of Curve Select the Center point of curve option to stake out the center point (1) of a defined curve (2). Figure 17.20 shows the text screen and a graphical representation of this option.

2

1

Figure 17.20 Stake to center point of curve

41 8

Trimble Survey Controller Reference Manual Volume 2

Page 451

GPS Stakeout

17.9

17

Staking Out a DTM To stake out a DTM: 1.

From the main menu, choose Survey. From the Select Survey Style menu, choose a real-time Survey Style. Then select Stakeout / DTMs. The Survey/Stakeout/DTM screen appears.

2.

Access the DTMs field. From the list, select the model to be staked out.

3.

If applicable, enter a value in the Vertical offset field.

4.

Enter a value in the Antenna height field.

5.

. The graphics screen appears. It displays the Press coordinates of the current position and the vertical distance above (cut) or below (fill) the DTM.

6.

. The Trimble Survey Controller To record a point, press software measures the point.

7.

Press x = m to return to the Survey/Stakeout/DTM screen.

Trimble Survey Controller Reference Manual Volume 2

419

Page 452

17

GPS Stakeout

42 0

Trimble Survey Controller Reference Manual Volume 2