Page 133

Job Operations

6

The ratio display can be in one of two formats, Rise:Run or Run:Rise. Figure 6.4 shows the difference between these.

pe Slo

Rise

Run

Figure 6.4

Rise and run in the grade display

The setting in the Laser VA display field determines whether the laser measurements are displayed as vertical angles measured from the zenith, or inclinations measured from horizontal. Use the HA VA angle display field to specify how horizontal and vertical angles are displayed. 4.

6.8

Press

\ to accept the settings and return to the Job menu.

System Settings and Corrections Various settings and corrections affect how data and results are displayed on the TSC1 data collector. It is important to understand the effects of the settings used. Note – If you change the settings in a subsequent job, the original job retains its settings. When you change a setting, a Note is recorded in the job database. Corrections applied to measurements made using conventional instruments are stored in the Conventional Survey Style.

Trimble Survey Controller Reference Manual Volume 1

103

Page 134

6 6.8.1

Job Operations

Cogo Settings Screen To access the list of settings and corrections, select Configuration from the main menu. Then select Job / Cogo settings. Figure 6.5 shows the Cogo settings screen that appears.

Figure 6.5

Cogo Settings screen

Change these settings as required. They are applied to the current job (if one is open) or to the next job you create.

6.8.2 o

Options Softkey An softkey appears in some of the screens that you reach by selecting Cogo from the main menu. Press it to change some settings and corrections (for example, Distances). Note – Parameters set in the Options screen only apply to the current job. Different jobs can have different settings.

10 4

Trimble Survey Controller Reference Manual Volume 1

Page 135

Job Operations

6

Distance Display

6.8.3

The Distances field defines how distances are displayed and which distances are used for calculations in the Trimble Survey Controller software. Select one of the following options: •

Ground (the default setting)

•

Ellipsoid

•

Grid

Figure 6.6 shows these options between the points A and B.

B Ground distance

A Grid distance Ellipsoid distance Ellipsoid Figure 6.6

Distances used by the Trimble Survey Controller software between points A and B

Note – Distance and height/elevation fields have the suffix (grid), (grnd), or (ell), depending on the value in the Distances field. Ground distance A ground distance is the horizontal distance calculated between the two points at the mean elevation parallel to the chosen ellipsoid. If an ellipsoid has been defined in the job and the Distances field is set to Ground distance, the distance is calculated parallel to that. If no ellipsoid has been defined, the WGS-84 ellipsoid is used. Trimble Survey Controller Reference Manual Volume 1

105

Page 136

6

Job Operations

Ellipsoid distance If the Distances field is set to Ellipsoid then a correction is applied and all distances are calculated as if on the local ellipsoid, which usually approximates to sea level. If no ellipsoid has been specified, the WGS-84 ellipsoid is used. Note – If the coordinate system for a job is defined as Scale factor only, ellipsoid distances cannot be displayed. Grid distance If the Distances field is set to Grid, the grid distance between two points is displayed. This is the simple trigonometrical distance between the two sets of two-dimensional coordinates. If the coordinate system for the job is defined as Scale factor only, and the Distances field is set to Grid, the Trimble Survey Controller software displays ground distances multiplied by the scale factor. Note – A grid distance between two measured GPS points cannot be displayed unless you have specified a datum transformation and a projection, or performed a site calibration.

6.8.4

Curvature Correction In the Trimble Survey Controller software system, all ellipsoid and ground distances are parallel to the ellipsoid. See Ellipsoid Calculations, page 200.

6.8.5

Azimuth Display The azimuth displayed and used by the Trimble Survey Controller software depends on the coordinate system that you defined for the current job: •

10 6

If you defined both a datum transformation and a projection, or if you selected Scale factor only, the grid azimuth is displayed.

Trimble Survey Controller Reference Manual Volume 1

Page 137

Job Operations

6

•

If you defined no datum transformation and/or no projection, the best available azimuth is displayed. A grid azimuth is the first choice, then a local ellipsoidal azimuth, then the WGS-84 ellipsoid azimuth.

•

If you are using a laser rangefinder, the magnetic azimuth is displayed.

In the Survey / Offsets screen you can select which azimuth is used. For more information, see Azimuths/Angles, page 596. Note – The azimuth that the Trimble Survey Controller software is using, is identified by the suffix (grid), (local), (WGS84), or (mag).

6.8.6

South Azimuth If a south azimuth display is required, set the South azimuth field to Yes. All azimuths still increase clockwise. Figure 6.7 shows the effect of setting the South azimuth field to No or Yes. N

N

0

180

270

90

90

270

180

0

S

S

South azimuth = No

South azimuth = Yes

Figure 6.7

South azimuth setting

Trimble Survey Controller Reference Manual Volume 1

107

Page 138

6 6.8.7

Job Operations

Grid Coordinates Use the Grid coords field to set the grid coordinates to increase in one of the following sets of directions: • North and East

• South and West

• North and West

• South and East

Figure 6.8 shows the effect of each setting. N

N

(–50,–50)

(50,50)

(–50,–50)

(50,50)

S

S Increase South-West

Increase North-East

N

N (–50,–50)

(50,50)

(–50,–50) S Increase North-West

Figure 6.8

10 8

(50,50) S Increase South-East

Grid coordinates setting

Trimble Survey Controller Reference Manual Volume 1

Page 139

Job Operations 6.8.8

6

Magnetic Declination Set the magnetic declination for the local area if magnetic bearings are being used in the Trimble Survey Controller software. You can use magnetic bearings if you choose the Brng-dist from a point method in the Survey/Offsets screen. Enter a negative value if magnetic north is west of true north. Enter a positive value if magnetic north is east of true north. For example, if the compass needle points 7° to the east of grid north, the declination is +7° or 7°E. Note – Use the published declination values if available.

6.8.9

Subdivide Pts Code When you subdivide a line or curve, a number of points are created. Use the Subdivide pts code field to specify what code the new points will get. Choose from the name or the code of the line or curve that is to be subdivided.

6.8.10

Default Elevation If a point has no elevation, the Trimble Survey Controller software uses the default elevation for Cogo calculations. If you combine GPS and two-dimensional conventional observations, set the Default elevation field to approximate the elevation of the site. The default value is null (?). This elevation is used with 2-D points to calculate grid and ellipsoid distances from measured ground distances. If you have defined a projection and you intend to do a 2-D survey, you must enter a value for the default elevation. This reduces measured ground distances to ellipsoid distances.

Trimble Survey Controller Reference Manual Volume 1

109

Page 140

6

110

Job Operations

Trimble Survey Controller Reference Manual Volume 1